Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & PartnersThe practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
![]() |
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
Publicitate pe BizLawyer? |
![]() ![]() |
Articol 797 / 4435 | Următorul articol |
Publicitate pe BizLawyer? |
![]() |

LegiTeam: CMS CAMERON MCKENNA NABARRO OLSWANG LLP SCP is looking for: Associate | Corporate and M&A Practice Group (2-4 years definitive ̸ qualified lawyer)
Solida Capital face prima tranzacție în România și anunță extinderea strategică pe piața din Europa Centrală și de Est | Cumpărătorul a fost asistat de Kinstellar, CMS a acordat consultanță vânzătorului pe aspecte fiscale și financiare, iar PNSA a fost alături de banca finanțatoare. Ce alți consultanți au fost implicați
LegiTeam: WH Simion & Partners is looking for an Associate ̸ Senior Associate
Rising Star | Alexandra Iancu, unul dintre cei mai buni absolvenți ai promoției 2022, a ales echipa ZRVP. ”Odată intrat în profesie, media de la facultate nu mai contează atât de mult, pentru că „examenele” din practică au alte criterii de reușită și este important să demonstrezi că te vei putea încadra în aceste criterii”
Schoenherr anunță câștigătorii concursului de eseuri „law, sweet law‟
Cum îi sprijină avocații GNP Guia Naghi și Partenerii pe clienții care solicită asistență în proiecte de obținere și implementare a ajutoarelor de stat și ce anume fac pentru a le spori șansele de succes | Manuela Guia (Managing Partner): „Considerăm că ar fi benefic să se acorde o atenție sporită industriilor cu potențial ridicat de creștere, cum ar fi tehnologiile verzi și digitalizarea. De asemenea, ar fi utilă o simplificare a procesului administrativ, pentru a facilita accesul mai rapid la finanțare și a reduce incertitudinea pentru investitori”
Lista scurtă a finaliștilor “Chambers Europe Awards - 2025” | Cinci firme din România luptă pentru trofeu: CMS, NNDKP și ȚZA, prezențe constante la gala premiilor, Mușat & Asociații intră în competiție propulsată de activitatea intensă din ultimul an, iar Filip & Company este nominalizată pentru a patra oară consecutiv
GNP Guia Naghi și Partenerii îl promovează pe Tudor NACEV ca Partener coordonator al practicii Regulatory Pharma și Achiziții Publice. El a asistat clienți importanți în proiecte de anvergură
Chambers Global 2025 | RTPR rămâne singura firmă de avocați listată pe prima poziție în ambele arii de practică analizate: Corporate ̸ M&A și Banking & Finance. Filip & Company și Schoenherr sunt în prima bandă în Corporate ̸ M&A. Firmele care au cei mai mulți avocați evidențiați sunt RTPR (9), Filip & Company (7), CMS (5) și Clifford Chance Badea (5)
Rising Stars | Bianca Bănățeanu, șef de promoție al seriei I a generației anului 2024 a decis să se îndrepte spre magistratură: ”Am ales să susțin probele de admitere la INM, după ce am oscilat de câteva ori între avocatură și magistratură. Sunt conștientă de responsabilitatea pe care o implică profesia de judecător, însă satisfacția pe care o simți atunci când știi că ai contribuit la înlăturarea unei situații de inechitate, la soluționarea unor probleme cu care oamenii se confruntă zi cu zi, mi se pare de neegalat”
Cum văd coordonatorii departamentelor juridice din companiile mari industriile în care activează și provocările anului 2025 | Monica Constantin, Legal & Corporate Affairs Director Bergenbier SA: ”Echipele noastre colaborează strâns pentru a preveni riscurile ce vin cu toate schimbările legislative. Vom continua acțiunile de conformare la modificările legislative și pe cele de prevenție. Menținem focusul pe strategia de sustenabilitate și continuăm să investim în dezvoltarea echipei”
Trei ofertanți intră în a doua rundă a vânzării Amethyst Healthcare, lanț paneuropean de radioterapie cu șase clinici în România. Goldman Sachs supraveghează tranzacția
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...